1. Why is TxDOT considering replacing Harbor Bridge?
Answer: TxDOT has determined that US 181 and the Harbor Bridge
must be improved to maintain a safe and efficient transportation corridor.
The existing bridge has safety issues associated with the lack of shoulders,
steep grade, a reverse curve, and an accident rate that is higher than
the statewide average. The Harbor Bridge also has high maintenance costs
and provides no acceptable access for those on foot or on bicycles. Furthermore,
the bridge's 138 feet of navigational clearance, which met World War II
standards when it was built, make it difficult for the Port of Corpus
Christi to compete with other Gulf Coast deep water ports because of larger
ship sizes today.
A new bridge would allow TxDOT to improve safety, thereby reducing
accident rates; provide better opportunities for moving people and goods
(including military equipment and Port assets) throughout the region;
provide adequate capacity to meet future traffic demand; and provide
greater economic development opportunities for the Port of Corpus Christi.
2. How will TxDOT decide whether or not to replace Harbor Bridge?
Answer: Before it can make any decision about the Harbor
Bridge, TxDOT must complete a series of project activities to ensure
that all aspects of a possible new bridge have been considered. In the
summer of 2003, TxDOT completed a Feasibility Study, which evaluated
four alternative corridors (including the existing one) where a replacement
of the Harbor Bridge might be located. The "no-build" option-leaving
the bridge as it is now--was also examined. Now TxDOT is working on
two other key activities-preparing the environmental documentation that
is required before any new bridge could be built-and the schematic design-developing
the preliminary engineering designs for a new bridge, associated approaches,
and tie-ins to existing roadways. The results of the environmental study
and schematic design, including a considerable amount of public input,
will enable TxDOT to decide on a bridge replacement.
3. What is an Environmental Impact Statement?
Answer: An Environmental Impact Statement (EIS) is a document
required by the National Environmental Policy Act (NEPA) for large projects
that use federal funds. It provides a detailed analysis of the probable
environmental consequences of the preferred alternative(s) for a project.
The EIS also considers the environmental consequences of the no-build
alternative. Public input is considered throughout the EIS development
process. The EIS must be reviewed by various state and federal regulatory
agencies, and must ultimately be approved by the U.S. Environmental
Protection Agency and the Federal Highway Administration.
4. When will the EIS be ready for the public to review?
Answer: A draft EIS will be ready for public comment sometime
in early 2007. A more detailed project
timeline can be found on this website.
5. When might a new bridge be in place?
Answer: Many factors affect the timing of a possible bridge
replacement. The purpose of the current environmental documentation
phase is to come up with a recommendation regarding the proposed alternatives
(including the "no-build") and to obtain environmental clearance
to proceed. Once TxDOT has received environmental clearance for the
project (anticipated to be sometime in 2008), the timing for bridge
construction will depend on the availability of funding. With the use
of innovative financing, bridge construction would be accelerated and
might begin as soon as 2010- 2015.
6. Why will it take so long to replace Harbor Bridge?
Answer: The process of planning and building a project of
this size takes many years (see project
timeline). TxDOT completed a feasibility study in 2003 and is now
compiling the environmental documentation and preparing the schematic
design for a possible bridge replacement. During these stages of the
project, public input is sought and considered. If the project is given
the go-ahead, the right-of-way must be obtained, the detailed design
developed, and the bridge constructed. Throughout the entire process,
various state and federal agencies must review and approve the environmental
documentation and the proposed plans. Furthermore, TxDOT must obtain
the funding to build a bridge, if that is the selected alternative.
7. How much will a new bridge cost to build?
Answer: At this point, TxDOT estimates that it may cost about
$500-600 million to build a new bridge and the associated approaches
and tie-ins, should the final decision be made to replace Harbor Bridge.
8. What would a new bridge look like?
Answer: Harbor Bridge is currently a steel truss-style bridge
over a highly corrosive saltwater environment. It is still too early
in the process to determine the look of a new bridge. Local citizens
will have a chance to offer ideas about the design of a new bridge during
a Design Guideline Workshop to be held in 2007. At that time, the bridge
architects and planners will present some possible bridge design ideas
and will seek ideas from the public.
9. Will I be able to walk or bicycle across a new bridge?
Answer: Currently the existing Harbor Bridge does not provide
any bicycle lanes and the sidewalk is closed to the public; however,
the City of Corpus Christi and Nueces County have identified Harbor
Bridge as a desired link in their recently adopted Bicycle and Pedestrian
Master Plans.
The plan is for any new bridge to provide access for pedestrians and
bicyclists, as well as motor vehicles.
10. Will there be a toll to drive on the new bridge?
Answer: Across the state, Texas is experiencing tremendous population
growth and therefore the need for new roads to address increased traffic
volumes. In the past, we have funded new facilities with gas tax revenues
paid by every driver when he/she purchases gas. However, the gas tax
at its current level does not raise enough money to build and maintain
new roads.
TxDOT must look at all potential sources of funding, including tolls
for new highway routes and added lanes on existing routes. Without some
type of innovative funding, projects will be delayed or cancelled for
lack of funds.
Corpus Christi is one of eight metropolitan areas of Texas that has
developed a Metropolitan Mobility Plan to address the use of new types
of financing to increase local mobility.
In the case of the Harbor Bridge, TxDOT is considering various types
of funding mechanisms including "managed"
lanes for any added capacity on a new bridge. In other words, if the
new bridge were to have eight lanes instead of the current six, those
two new lanes might be managed lanes with a toll. Because it is TxDOT's
policy not to toll existing capacity, the replacement of the current
six lanes would not be tolled.
Therefore, drivers would have a choice of driving in non-tolled lanes
or paying to drive in a managed lane. The advantage to a driver of using
a managed lane would be a shortened drive time across the bridge during
periods of traffic congestion.
11. How much would I pay for the toll?
Answer: If TxDOT determines that managed lanes are needed
to provide funding for a new bridge, the agency will determine the amount
of the toll on the basis of the projected future traffic across the
bridge and the costs of constructing and maintaining the bridge.
12. Where would a new bridge cross the Corpus Christi Ship Channel?
Answer: The location has not yet been determined. The Feasibility
Study completed in 2003 identified four possible corridors and identified
one of those as a preferred alternative. However, the Federal Highway
Administration has asked TxDOT to look at several of these alternatives
(including the no-build) during the environmental documentation/schematic
design phase of the project.
13. How would a new bridge tie into the existing road system in
Corpus Christi?
Answer: The schematic design currently being developed will
evaluate various options for connecting a new Harbor Bridge and its
approaches to the Crosstown Expressway (SH 286). Public input on access
ramps and approaches is being considered throughout this process.
14. How will a new bridge affect neighborhoods near the old bridge?
Answer: During the environmental documentation process, TxDOT
will be considering the impact of any new structure on the nearby neighborhood
homes and businesses. These impacts will be described in the EIS. Comments
from the public about potential neighborhood impacts are important input.
15. How can I participate in the Harbor Bridge project?
Answer: Public involvement is a key element of the Harbor Bridge
project. You can participate in the project in a number of ways. At
the project's public meetings and
hearing, you can learn more about the project and provide comments.
You can join the Citizens'
Advisory Committee (CAC), which has regular informal meetings with
TxDOT to exchange information. You should also continue to monitor the
project website for new developments.
16. What is the Citizens' Advisory Committee?
Answer: The Citizens' Advisory Committee (CAC) offers the
community an opportunity for a timely exchange of information with TxDOT
about the Harbor Bridge project. During these meetings, TxDOT and its
consultant provide a project status report and seek the group's input
on upcoming public involvement activities. The committee meets about
twice a year (more frequently if needed) both in Corpus Christi and
in Portland.
17. How can I become a Citizens' Advisory Committee member?
Answer: Membership is open to anyone with an interest in
the project and a commitment to attend meetings. Contact the TxDOT
project manager for more information.
|